*Note this form is for informational purposes only – the actual form will be completed online.


SEU Use Only

Application Number: ________________

Bid Date: ________________

Intake Personnel: ________________

Application Complete: Yes/No

APPENDIX A
Form of Bid Application

APPLICATION

to sell

SOLAR RENEWABLE ENERGY CREDITS

2011 SREC PROCUREMENT PILOT PROGRAM

 

This is an application to sell solar renewable energy credits (“SRECs”) to the Delaware Sustainable Energy Utility, Inc. (the “SEU”) pursuant to a pilot procurement program for the 2011 compliance year established in accordance with the Delaware Renewable Energy Portfolio Standards Act (as amended, “REPSA”).

Owner Information[24]

Name (company or individual): _______________

Street address: _______________

City, state and zip code: _______________

Email address: _______________

GATS Account No.:[25] _______________

Other Eligible Energy Resources
owned by Owner:[26] _______________

Owner Representative Information (to be filled in if applicable)[27]

Name (company or individual): _______________

Street address: _______________

City, state and zip code: _______________

Email address: _______________

GATS Account No.: _______________

Other Eligible Energy Resources
owned by Owner Representative: _______________

Description of Project

Location: _______________
(street address or parcel number)

City, state and zip code: _______________

Nameplate capacity (kW-DC)[28] _______________

Tier designation (check one):

¨ Tier 1 Project (less than or equal to 50 kW-DC)

¨ Tier 2-A Project (greater than 50 kW and less than or equal to 250 kW-DC)

¨ Tier 2-B Project (greater than 250 kW and less than or equal to 500 kW-DC)

¨ Tier 3 Project (greater than 500 kW and less than or equal to 2,000 kW-DC)

Module type (make and model): _______________

Inverter type (make and model): _______________

System tilt (degrees): ________________

System azimuth (degrees): ________________

Mounting location (specify one):

¨ Ground

¨ Rooftop

Operational status (check one):

¨ Project currently under development

¨ Project currently in operation
Specify initial operation date: _______________

Estimated energy and SREC output:

First-year energy output: ______ kWh (exclusive of any bonuses described below)

First-year SREC output: ______ SRECs (exclusive of any bonuses described below)

Utility interconnection:

_______________ Interconnecting Utility

_______________ Date of acceptance of completed System Interconnection Application

Required Information

Supplemental funding from public sources[29] (provide information for any funding applied for, awarded and/or received):

¨ Delaware Green Energy Program Grant
Application Date: _______________
Utility _______________
Award Date: _______________
Amount: _______________

¨ Other public supplemental funding (provide additional sheet if necessary)
Source: __________________________________
Application Date: __________________________________
Award Date: __________________________________
Amount: __________________________________

Eligibility for Delaware Equipment Bonus (check if applicable):

¨ The Project is sited in the State of Delaware and a minimum of 50% of the total cost of renewable energy equipment, inclusive of mounting components, is manufactured in Delaware[30]

Eligibility for Delaware Workforce Bonus (check if applicable):

¨ The Project is sited in the State of Delaware and is or will be constructed and/or installed either with a workforce at least 75% of whom are Delaware residents or by a company that employs at least 75% Delaware residents[31]

Price Bid:[32] $_______________ per SREC (applicable during first 10 years)

[For any Owner of a Tier 1 or Tier 2-A project submitting a price bid]
THE UNDERSIGNED HEREBY ACKNOWLEDGES THAT BY SUBMITTING THE PRICE BID SET FORTH ABOVE, THIS APPLICATION WILL BE EVALUATED ON A COMPETITIVE BASIS WITH OTHER PRICE BIDS AND THAT IT WILL BE DEEMED TO HAVE WAIVED ANY AND ALL RIGHTS IT MAY HAVE PURSUANT TO THE 2011 SREC PROCUREMENT PILOT PROGRAM TO RECEIVE AN ADMINISTRATIVELY SET PRICE FOR SRECS GENERATED BY THE PROJECT.

_____________________________________
Owner

Print: _____________________________________

THE UNDERSIGNED HEREBY CERTIFIES THAT: (A) IT IS THE OWNER IDENTIFIED HEREIN; (B) THIS IS THE ONLY APPLICATION BEING SUBMITTED PURSUANT TO THE 2011 SREC PROCUREMENT PILOT PROGRAM THAT INCLUDES THE PROJECT DESCRIBED HEREIN; (C) THE INFORMATION SET FORTH IN THIS APPLICATION IS TRUE, ACCURATE AND COMPLETE; AND (D) IT HAS FULLY, COMPLETELY AND ACCURATELY IDENTIFIED ALL SUPPLEMENTAL FUNDING FROM PUBLIC SOURCES (OTHER THAN GRANTS IN LIEU OF INVESTMENT TAX CREDITS) FOR WHICH IT HAS APPLIED OR WHICH IT HAS BEEN AWARDED OR RECEIVED.

_____________________________________
Owner

Print: _____________________________________

Attachments

Completed SREC Transfer Agreement executed by Owner and, if applicable, Owner Representative

Deposit in the amount of $100/kW of the nameplate rating of the Project

Calculation of the estimated first-year energy output using PVWatts Solar PV Energy Calculator or other modeling technique acceptable to the SEU (using actual tilt and orientation)


[24] The designated Owner must be the legal entity that owns, leases, controls or is the direct assignee of all of the SRECs created by the Project described in this Application.

[25] Not required if an Owner Representative is designated or if construction of Project is not complete.

[26] Not required if an Owner Representative is designated.

[27] An Owner Representative must be designated unless: (a) the Project has an aggregate nameplate rating (as designated by the solar module manufacturer) of at least 100 kW (DC) at STC; or (b) the Owner has executed agreements to control the SRECs produced by at least one other Eligible Energy Resource.

[28] At standard test conditions (internal cell temperature of 25°C and irradiance of 1,000 watts per square meter with air mass 1.5 spectrum).

[29] Excluding any grants in lieu of investment tax credits.

[30] Eligibility for the Delaware Equipment Bonus shall be determined solely by the DPSC.

[31] Eligibility for the Delaware Workforce Bonus shall be determined solely by the DPSC.

[32] For all Tier 2-B and Tier 3 Projects and for any Tier 1 and Tier 2-A Projects that have elected to waive their right to receive an administratively set price.